Posted: November 5th, 2015

Time Cost CPM scheduling analysis table

Time Cost CPM scheduling analysis table

Question 16: Time-Cost CPM Scheduling Model Analysis

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days.

Activity
Immediate Predecessor
Normal Time
Crash Time
Normal Cost
Crash Cost
A
None
4
3
$213
$397
B
A
4
3
$307
$623
C
A
1
1
$212
$212
D
B and C
5
4
$503
$551
E
D
4
3
$494
$897

Part b: 4 points

What are the total normal cost of this project? Please give your answer in $.
Locally stored answer:

Part c: 6 points

If you crash this project to reduce the total time by one day (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer:

Part d: 6 points

If you crash this project to reduce the total time by three days (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer:

PLACE THIS ORDER OR A SIMILAR ORDER WITH US TODAY AND GET A GOOD DISCOUNT 🙂

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp