Time Cost CPM scheduling analysis table
Question 16: Time-Cost CPM Scheduling Model Analysis
Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days.
Activity
Immediate Predecessor
Normal Time
Crash Time
Normal Cost
Crash Cost
A
None
4
3
$213
$397
B
A
4
3
$307
$623
C
A
1
1
$212
$212
D
B and C
5
4
$503
$551
E
D
4
3
$494
$897
Part b: 4 points
What are the total normal cost of this project? Please give your answer in $.
Locally stored answer:
Part c: 6 points
If you crash this project to reduce the total time by one day (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer:
Part d: 6 points
If you crash this project to reduce the total time by three days (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $.
Locally stored answer: