Posted: September 16th, 2015

Project Man.

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget Begun? Complete? Actual cost Earned Value
Task A 3,100 Yes Yes 3,100
Task B 4,000 Yes Yes 4,500
Task C 2,500 Yes Yes 2,250
Task D 4,000 Yes No 3,500
Task E 3,500 Yes Yes 4,000
Task F 2,500 No No 0

 

  • Using the 50-50 Rule, what is earned value for this project?
  • Using the 0-100 Rule, what is earned value for this project?
  • Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  • Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  • What is the schedule performance index (SPI)?
  • Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  • What is the cost performance index (CPI)?
  • If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
  • Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Looking for the best essay writer? Click below to have a customized paper written as per your requirements.

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp