Month ACWP BCWS BCWP 5 $34 $42 $39 a) Calculate the CPI (Cost Performance Index). [2 points] b) Is the project cost efficient or not efficient? [2 point] c) Calculate the SPI (Schedule Performance Index) [2 points] d) Is the schedule efficient or not efficient? [2 point