Posted: July 8th, 2015
Project Analysis
Introduction
The project shall be completed on September 25, 2015. I will have two servants to clear the land for a duration of 2 days. The servants shall burn the trash on the third day. They will then till the land for the remaining part of the week. The seeds will be planted in the next week. I will start watering the seeds immediately after planting. Watering shall stop after a week of planting since the heavy rains would have started. I will plant the early girl type of seeds which will take 6 weeks to grow. Pruning will be done every day for a duration of three weeks then stop once since the seedlings will have grown. At this time the tomato plants will be big enough to provide a canopy over the land and consequently help in preventing weeds from growing. The pruning will be done using rudimentary tools such as hoes. I will fix a scarecrow on the third week after planting so as to scare away tomato eating birds.
Tomatoes will be ready by the sixth week after preparation of the land. I will then harvest the tomatoes on the 17th of September. I will then store the tomatoes with the city storage facilities. The tomatoes will be stored for a week in the storage facility waiting transportation. The tomatoes will then be transported to the processing plant after the week of storage.
“Tomato project” Analysis
Activity | Dates | Task Duration |
Removal of trees and clearing of the land for 2 days | 29th July 2015 | 2 day |
Burning of trash for 1 day. | 1st August 2015 | 1 day |
Tilling the land for 3 days | 4th august 2015 | 3 days |
Planting of seeds | 6th August 2015 | 1day |
Watering of the seeds | 13th August 2015 | 6 days |
Pruning | 26th August2015 | 21 days |
Tomatoes mature | 17th September 2015 | 42 days |
Storage of tomatoes | 24th September2015 | 7 days |
Transportation | 25th September 2015 | 1 day |
Table1: Tomato Project Analysis. Source: Self.
I had to mitigate the risk of my crops being eaten by birds. I would use scarecrows to scare the birds away. Task dependency enables easy and accurate drawing of the project network diagram. The factors that I took into account when determining the schedule/Gantt chart and network diagram were: the time that would be taken by the project, the nature of the project, he number of people doing the project and the challenges of the project (Hamilton, Byatt, & Hodgkinson, 2015). The challenges of the project were
Conclusion
Project management enables the planning and executing of tasks in order to achieve intended objectives. Project management is therefore an important tool during implementation of projects and hence should not be overlooked (Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 2013). The tomato growing project as for financial gains since I sold the tomatoes when they matured (Pminyc, 2015).
Hamilton, G., Byatt, G., & Hodgkinson, J. (2015, June 10). Explaining Risk Mitigation in Project Management. Retrieved from http://www.cio.com.au/: http://www.cio.com.au/
Pminyc. (2015, March 29). Why is Project Management important? Retrieved from PMINYC: http://www.pminyc.org/
Project Management: A Systems Approach to Planning, Scheduling, and Controlling. (2013). New Jersey: John wiley & sons.