Question 2:
Part No. | Routing (Operation Sequence) |
X | A-C-H-G-E-F-I |
Y | A-C-E-G-I |
Z | A-H-F-B-D-G-I |
Part No. | Quantity per Day | Weight in kgs | Total Weight (kgs) | Relative Importance |
X | 300 | 1 | 300 | 3.0 |
Y | 100 | 1 | 100 | 1.0 |
Z | 200 | 1 | 200 |
A company produces screwdrivers represented in figure. 3.1. The main operation sequence for the tool is shown in figure 3.2, and figure 3.3 (for the handle). A hydraulic press is used for the assembly of the tool and handle. Use the information given to develop the operations chart for the screwdrivers shown in figure 3.1.