Posted: November 14th, 2015
Loading chart for the project resources
1. Complete the network diagram by conducting a forward and backward pass through the network. Compute the
early/late start time, early/late finish time, and slack time for each activity
2. What is the project duration?
3. What is the critical path of this network?
4. Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources:
Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are
available.
5. Using the resource loading chart, now compute the early/late start time, early/late finish time, and
slack time for your project. Illustrate this new resource constrained network in a network diagram.
6. Complete the resource activity schedule.
7. For the new network, what is the new project duration?
8. Which activities are now critical?
PLACE THIS ORDER OR A SIMILAR ORDER WITH US TODAY AND GET A GOOD DISCOUNT 🙂
Place an order in 3 easy steps. Takes less than 5 mins.