Hydraulic services.

Sanitary drainage will connect to this main via a sewer boundary trap
(SBT) located within the property on the northern boundary. Design is required to upstream
side of SBT only.
Stormwater: Stormwater will discharge to a below-grade SDT in southern boundary carpark (see location
and plan dimensions on drawing) and then to the western kerb of the street. The gutter
discharge RL will need to be determined as part of the exercise. Use rainfall intensity data for
Rockhampton based on 20 minute duration (1 0 year ARI) and accept that Local Council
requires a design based on maximum 90L/s/Ha allowable runoff (i.e. your exercise is to
nominate the SDT depth based on inflow versus allowable outflow at the 20minute peak).
Potable water: DN100 main located in western footpath to the street, with invert at a constant 1.0m below
footpath. The supply authority can only guaranteed a pressure of 1 8mH and because it is in a
new growth area of the city, you need to install a surge tank as the mandatory design. You
must achieve 150kPa at the most disadvantaged outlet. Consider carefully the facilities and
determine overall capacity (mH and L/s) for a pressure set serving the development from a
surge tank location that you will note on your drawings.
Assessment Criteria
Using your appreciation of hydraulics installations to all levels of the building (Under-floor, ground and first floors
and roof), determine the following
1. Cold Water Supply System
Recommend a reticulation system. Provide a single line diagram of the system, indicating pressure zones,
loading units, select pipe sizes to limit velocity to acceptable limits and pressure sets requirements.
a). Single line diagram
 Loading units
 Pipe sizes
b). Pressure set capacity (in mH and Q)
2. Roof Areas Drainage System
Design the stormwater drainage system. Provide a single line diagram showing the collection system, including
flow rates, pipe sizes and falls to detention tank, the location of which is at your discretion. Determine detention
tank capacity.
Page 2 of 3
a). Assumptions
 Storm intensity calculations
b). OSD tank
 Capacity calculations
3. Sanitary Plumbing and Drainage System
Design the sanitary plumbing and sanitary drainage system, including sizing of pipe work from pans, urinals,
basins, showers and sinks.

Looking for the best essay writer? Click below to have a customized paper written as per your requirements.

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp