In a 1-page Word document, consider the following activities and their durations.

The original project schedule, using early activity starts, is shown below.

Activity    Task    Predecessors    Duration    Activity Cost
A    Sign Contract    None    5 days    $5,000
B    Design Survey    A    3 days    $1,500
C    Identify Audience    A    7 days    $1,000
D    Run Survey    B, C    30 days    $6,000
E    Analyze Results    D    5 days    $3,000
F    Create Presentation    E    5 days    $1,000
G    Present to Client    E, F    2 days    $3,000
Reconfigure the chart above into a critical path diagram for project scheduling

similar to the diagram shown in this module’s lecture.
What is the duration of the project?
How much slack is currently available in the non-critical path?
How long are the project and feeder buffers?

PLACE THIS ORDER OR A SIMILAR ORDER WITH US TODAY AND GET A GOOD DISCOUNT 🙂

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp