Use the network diagram below and the additional information provided to answer the corresponding questions. [13 points] .jpg” alt=”Crashing network 2“> a) The crash cost per day per activity. [10 points] b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities? [3 points]